Abaco Hurricane Shelter ‘progressing’ despite inherited delays

Tue, Mar 5th 2024, 10:14 AM

The new, State-of-the-Art Hurricane Shelter and Community Centre currently under construction in Central Pines, Abaco, is scheduled to be fully completed by November 2024, despite some inherited delays.

Contractors add that the dual Shelter/Community Centre, which is anticipated to be a prototype for the future design and construction of shelters in The Bahamas, will have an “occupied date” of early summer, meaning that the facility should be available to host those persons requiring assistance at that time, if the need arises.  This is good news as the 2024 Atlantic Hurricane Season begins June 1 and runs through November 30.  Abaconians will continue to have access to a host of other approved shelters throughout the island, and not just rely on the prototype alone, however.

Disaster Risk Management officials further say the dual Hurricane Shelter and Community Centre will be “one of a kind” in the region in terms of its construction and design. The building is being constructed under “a new building code,” that calls for its structure – doors, window, roof -- to withstand hurricane force winds of up to 250 miles per hour (Category 5 Hurricane and higher).

Its mechanical systems are designed to accommodate diverse loads, including an industrial kitchen, communication systems, air-conditioning system, male and female bathrooms and showers, office spaces for emergency personnel, in addition to storage areas.

Standby generators to ensure continuity with communications, water, sewerage, air-conditioning, refrigeration, safety and security, will be installed in order to mitigate the impacts of disruptions in power.

A ramp that was not included in the original design, was added to allow persons with disabilities and the elderly -- considered two of the more vulnerable populations particularly during natural disasters such as tropical storms and/or hurricanes -- easy frontal access to the facility under the protection of a canopy.

“Construction is going very well, particularly now that we are back on schedule,” said Mr. Chris Symonette, Project Manager. “We had lost almost a year due to some faults that we found in the ground, and in the foundation, we met in place when we assumed responsibility for the project. These corrective measures took us about 9 months to resolve.

“The building is one of a kind in the region. As a matter of fact, this will be the first 250 miles-per-hour hurricane shelter design in The Bahamas. We had to exceed the ratings while ensuring that we have redundancy upon redundancy,” Mr. Symonette added.

Raeh Williams, a Director, with Wilkem Solutions, a Bahamian-owned entity that specializes in development, civil works and waste management, among other services, said the construction team has been “pushing every day” to ensure that they meet the projected dates. The company took over construction operations a little over one year ago.

“We met a lot of challenges that were a real test of our skill and tenacity because there were caves, holes and a lot of other issues that basically caused us to have to perform a lot of corrective work to get us where we are today. The scheduled completion date is November 2024, but we are anticipating having an occupied completion by June/July which is right at the beginning of the Hurricane Season so that if there is some need to use the shelter, it will be available. That is our push and we are pushing every day to make sure that we stick to that.”

The new, State-of-the-Art Hurricane Shelter and Community Centre currently under construction in Central Pines, Abaco, is scheduled to be fully completed by November 2024, despite some inherited delays.
Contractors add that the dual Shelter/Community Centre, which is anticipated to be a prototype for the future design and construction of shelters in The Bahamas, will have an “occupied date” of early summer, meaning that the facility should be available to host those persons requiring assistance at that time, if the need arises.  This is good news as the 2024 Atlantic Hurricane Season begins June 1 and runs through November 30.  Abaconians will continue to have access to a host of other approved shelters throughout the island, and not just rely on the prototype alone, however.
Disaster Risk Management officials further say the dual Hurricane Shelter and Community Centre will be “one of a kind” in the region in terms of its construction and design. The building is being constructed under “a new building code,” that calls for its structure – doors, window, roof -- to withstand hurricane force winds of up to 250 miles per hour (Category 5 Hurricane and higher).
Its mechanical systems are designed to accommodate diverse loads, including an industrial kitchen, communication systems, air-conditioning system, male and female bathrooms and showers, office spaces for emergency personnel, in addition to storage areas.
Standby generators to ensure continuity with communications, water, sewerage, air-conditioning, refrigeration, safety and security, will be installed in order to mitigate the impacts of disruptions in power.
A ramp that was not included in the original design, was added to allow persons with disabilities and the elderly -- considered two of the more vulnerable populations particularly during natural disasters such as tropical storms and/or hurricanes -- easy frontal access to the facility under the protection of a canopy.
“Construction is going very well, particularly now that we are back on schedule,” said Mr. Chris Symonette, Project Manager. “We had lost almost a year due to some faults that we found in the ground, and in the foundation, we met in place when we assumed responsibility for the project. These corrective measures took us about 9 months to resolve.
“The building is one of a kind in the region. As a matter of fact, this will be the first 250 miles-per-hour hurricane shelter design in The Bahamas. We had to exceed the ratings while ensuring that we have redundancy upon redundancy,” Mr. Symonette added.
Raeh Williams, a Director, with Wilkem Solutions, a Bahamian-owned entity that specializes in development, civil works and waste management, among other services, said the construction team has been “pushing every day” to ensure that they meet the projected dates. The company took over construction operations a little over one year ago.
“We met a lot of challenges that were a real test of our skill and tenacity because there were caves, holes and a lot of other issues that basically caused us to have to perform a lot of corrective work to get us where we are today. The scheduled completion date is November 2024, but we are anticipating having an occupied completion by June/July which is right at the beginning of the Hurricane Season so that if there is some need to use the shelter, it will be available. That is our push and we are pushing every day to make sure that we stick to that.”
 Sponsored Ads