Bridge toll doubles to 2

Tue, Jan 26th 2016, 12:39 PM

By RICARDO WELLS | Tribune Staff Reporter

THE Bridge Authority plans to double toll rates for private vehicles crossing the Sir Sidney Poitier Bridge from $1 to $2 per passage effective from March 1.

Rory Higgs, chairman of the Bridge Authority, made the revelation at a contract signing ceremony yesterday. He was unable to give the complete scope of the proposed fee increases but said his organisation intends to present a full fee schedule in the coming weeks. He said the rate increase would offset the cost of refurbishment specifically for the eastern bridge and maintenance expenses for both overpasses linking Paradise Island to New Providence.

The Bridge Authority signed a $5,359,421.50 agreement with local engineering firm Island Site Development to carry out repairs on the eastern overpass after a detailed inspection of the bridge revealed that several components exhibited varying levels of deterioration which required some form of rehabilitation.

Mr. Higgs said the Bridge Authority concluded that it would be in the interests of safety and cost-effective practices to have the eastern bridge undergo immediate, comprehensive refurbishment with a scheduled replacement in 2042.

As a result of that decision, the Bridge Authority commenced a “rigorous” tender process in which 12 engineering firms expressed some degree of interest. Four asked to tender bids, three submitting bids and finally, Island Site Development was selected to carry out a 42-week redevelopment exercise.

This project, along with a number of others currently being carried out by the Bridge Authority, is the result of a $28m private placement bond being funded by shareholders through the Central Bank of the Bahamas. However, none of the parties present – government officials and officials from the Bridge Authority – could clarify specifics related to shareholders and the bond.

The Tribune understands that, to date, the Bridge Authority had managed only to repay roughly $6 million on the private placement bond.

Prime Minister Perry Christie, during his address at yesterday’s contract signing, insisted that the project signified the government’s continued effort to ensuring that infrastructure critical to the country’s development is constructed and maintained in the most cost-effective way.

Mr. Christie also made a point to stress the important role the bridge plays in the relationship between the Bahamas and the scores of resort properties operating at Paradise Island.

“This is a very significant part of the mainstay of our country,” he said.

“It is important that we pay attention to it and it is important that the hotel owners over on Paradise Island, the properties on Paradise Island, becomes a significant one where we are completely at one with them when it comes to protecting the future of this island.”

Ed Fields, senior vice president of public affairs for Atlantis, told reporters that while the premise of the contract signing aims to positively affect the country’s tourism product, the cost of the project has forced the Bridge Authority to hike toll fees, which he noted could be a negative drawback for Paradise Island.

Mr. Fields revealed that Atlantis subsidises nearly 50 per cent of toll fees for its employees – a figure some experts estimate could be in the tens of thousands dollar range.

Repair efforts are expected to get underway on the eastern bridge early next month.

Island Development Site President Larry Treco warned that while there may be some logistical issues with respect to traffic manoeuvring over the bridge and day-to-day operations for some vendors at Potter’s Cay Dock, his company intends to minimise its effect with the use of hydroplanes.

Mr. Treco said his company has been contracted to repair structural faults associated with the bridge’s piling columns above water and underwater; support beams; support girders and sidings.

Additionally, Labour Minister Shane Gibson indicated that some 30 to 40 Bahamians are expected to be employed as a part of the reconstruction efforts.

Last November, a decision by the Bridge Authority to add a VAT charge to tolls for all vehicles was met with staunch opposition, forcing the group to backtrack within days.

That proposed increase would have seen the toll for single axle vehicles increase from $1 to $1.08; $2 to $2.15 for double axles; and $3 to $3.23 for triple axle vehicles.

Click here to read more at The Tribune