New Category : Roadwork

Complete at last! Paving work on Village Road done

Wed, Mar 1st 2023, 08:05 AM

AFTER several delays, major work for the Village Road Improvement Project is finally completed, marking the end of a long, frustrating journey for motorists and business owners in the area.

However, several weeks of minor works remain to be completed, including signage, striping and traffic lights.  #Albrion Symonette, Jr, resident engineer of the Village Road Improvement Project, told reporters yesterday that paving of the road was completed. # The only thing left for contractors to do, he said, is a few minor works, which includes installing signage in the area along with traffic signals and repairing sidewalks that may have been damaged during the course of construction. # “We’ve achieved substantial completion on the Village Road Improvement Project, which means that we have completed the contract pavement. So, the underground works are completed, the pavement works are complete,” Mr Symonette said during a press conference at the site yesterday. # “What we have left to do includes striping work, signage work, as well as traffic signals so our intention is over the next few weeks to install the signage, install the striping, install signals, and to also ensure that we reinstate anything that was damaged during the course of the work. So sidewalks, curbs, walls and such were damaged.” # Mr Symonette could not give a definite timeline for the remaining work’s completion, but said it should take another few weeks to finish. # “We do not have a definitive timeline at the moment because we are waiting for the shipment of some items, primarily the traffic signal equipment,” he added. “There have been some global supply chain issues that have pushed the procurement date back for those traffic signals significantly, so we are looking to hopefully see those in a few weeks’ time.” # The completion date for the Village Road project was initially scheduled for September last year, but the deadline was missed and shifted to December before moving to January and then February. # Businesses in Village Road have previously lamented the shifting deadlines and have since requested an incentives package from the government to revive their businesses which they claimed suffered losses by the year-long roadworks. # In terms of future repairs, Mr Symonette was unable to guarantee there won’t be any road digging by utility companies in the months ahead. # However, he said: “We do our endeavour best to minimise and mitigate the future potential or need for it so what we’ve done is during the course of the works, we’ve incorporated a lot of underground works, wherein we have said ‘okay, we want to take this additional scope and do it now to prevent the urgent or the automatic need to go into the road.’ #“So, there’s never a guarantee, but we do our best to mitigate. What we’ve actually done is install conduits across the road so in the event, a utility company needed to cross the road rather than excavating the road, they’re able to use those spare ducts which they have actually used already. # “There have already been instances on Village Road where we’ve used the spare ducts to avoid having to excavate the roadway.” # The project has a price tag of $6.4m and according to Mr Symonette yesterday, it remains on budget.

However, several weeks of minor works remain to be completed, including signage, striping and traffic lights. 

Albrion Symonette, Jr, resident engineer of the Village Road Improvement Project, told reporters yesterday that paving of the road was completed.

The only thing left for contractors to do, he said, is a few minor works, which includes installing signage in the area along with traffic signals and repairing sidewalks that may have been damaged during the course of construction.

“We’ve achieved substantial completion on the Village Road Improvement Project, which means that we have completed the contract pavement. So, the underground works are completed, the pavement works are complete,” Mr Symonette said during a press conference at the site yesterday.

“What we have left to do includes striping work, signage work, as well as traffic signals so our intention is over the next few weeks to install the signage, install the striping, install signals, and to also ensure that we reinstate anything that was damaged during the course of the work. So sidewalks, curbs, walls and such were damaged.”

Mr Symonette could not give a definite timeline for the remaining work’s completion, but said it should take another few weeks to finish.

“We do not have a definitive timeline at the moment because we are waiting for the shipment of some items, primarily the traffic signal equipment,” he added. “There have been some global supply chain issues that have pushed the procurement date back for those traffic signals significantly, so we are looking to hopefully see those in a few weeks’ time.”

The completion date for the Village Road project was initially scheduled for September last year, but the deadline was missed and shifted to December before moving to January and then February.

Businesses in Village Road have previously lamented the shifting deadlines and have since requested an incentives package from the government to revive their businesses which they claimed suffered losses by the year-long roadworks.

In terms of future repairs, Mr Symonette was unable to guarantee there won’t be any road digging by utility companies in the months ahead.

However, he said: “We do our endeavour best to minimise and mitigate the future potential or need for it so what we’ve done is during the course of the works, we’ve incorporated a lot of underground works, wherein we have said ‘okay, we want to take this additional scope and do it now to prevent the urgent or the automatic need to go into the road.’

“So, there’s never a guarantee, but we do our best to mitigate. What we’ve actually done is install conduits across the road so in the event, a utility company needed to cross the road rather than excavating the road, they’re able to use those spare ducts which they have actually used already.

“There have already been instances on Village Road where we’ve used the spare ducts to avoid having to excavate the roadway.”

The project has a price tag of $6.4m and according to Mr Symonette yesterday, it remains on budget.

Road Closures & Diversions

Thu, Feb 16th 2023, 11:06 AM

Ministry Of Works Notice - Roads

Thu, Nov 10th 2022, 02:24 PM

Traffic Press Release Service Of Thanksgiving For The Late Sovereign Queen Elizabeth II

Mon, Oct 3rd 2022, 10:20 AM

A Service of Thanksgiving for the Late Sovereign Queen Elizabeth The Second will be held on Sunday, 2nd October, 2022 at 4:00 p.m. at Christ Church Cathedral, George Street.

ROAD CLOSURE:

On Sunday, 2nd October, 2022 from 12:00 a.m. until after the Thanksgiving Service, the following streets will be closed to vehicular traffic:

BAY STREET   - BOTH SIDES

LION AND FREDERICK STREETS  – BOTH SIDES

BANK LANE – BOTH SIDES

From 12:00 a.m. until after the Thanksgiving Service, vehicular traffic will be diverted to streets away from the service.  The public is asked to adhere to the changes.

NO PARKING

On Sunday, 2nd October, 2022 from 12:00 a.m. until after the Thanksgiving Service, no vehicles will be allowed to park on the following streets.

BANK LANE – BOTH SIDES

BAY STREET – BOTH SIDES

LION AND FREDRICK STREETS – BOTH SIDES

ALL SIDE STREETS WILL BE CLOSED

December delay for Village Road

Thu, Sep 22nd 2022, 09:18 AM

Step Street Set For Road Works

Mon, Feb 10th 2020, 09:16 AM

Public Notice - Road Works, Retirement Road and Virginia Street

Public Notice - Road Works, Retirement Road and Virginia Street

Wed, Jan 22nd 2020, 12:00 AM

The Ministry of Public Works/Bahamix in conjunction with Island Pavers, has scheduled road works for Retirement Road and Virginia Street.

Retirement Road

The Milling and surface preparation of Retirement Road will begin on Monday, February 3, 2020, between the hours of 7:00p.m. and 3:00a.m. for two (2) days.

The Paving works is programmed for Wednesday, February 5, 2020 thru Friday February 7, 2020, between the hours of 9:00a.m. and 2:30p.m.

Virginia Street

The Milling and surface preparation of Virginia Street will begin on Monday, January 27, 2020, between the hours of 9:00a.m. and 2:30p.m. for two (2) days.

The Paving works is programmed for Wednesday, January 29, 2020 Thru Friday, January 31, 2020, between the hours of 9:00a.m. and 2:30p.m.

Provisions will be made for local traffic where necessary. Motorists are asked to avoid the area if possible.

Please be aware of and acknowledge the posted traffic paving signs in the area.

If you have any queries or concerns, please feel free to contact us at telephone numbers (242) 361-3886 or (242) 341-3886.

Bahamix apologizes for any inconvenience caused.

PUBLIC NOTICE CARMICHAEL RD. / FAITH AVE. JUNCTION

PUBLIC NOTICE CARMICHAEL RD. / FAITH AVE. JUNCTION

Tue, Nov 5th 2019, 02:21 PM

The Ministry of Public Works/Bahamix, has scheduled paving works for the Junction of Carmichael Road and Faith Avenue.

The Road Works is scheduled to commence from 9:30am to 2:00pm, beginning Wednesday November 6th, 2019 until Friday November 8th, 2019.

There will be brief road and lane closures leading to the Junction.

You are asked to be aware of and acknowledge the posted traffic paving signs in the area.

If you have any queries or concerns, please feel free to contact us at telephone numbers (242) 361-3886 or (242) 341-3886.

The Ministry of Public Works/Bahamix apologizes for any inconvenience caused.