Miller warns BEC troubles will bring a long hot summer

Thu, Mar 26th 2015, 01:06 PM

CHAIRMAN Leslie Miller said Bahamians are in for a “long, hot, rough” summer as the Bahamas Electricity Corporation continues to experience challenges with generators at its two power plants.

Mr Miller’s comments came after four engines at Clifton Pier and two at Blue Hills, failed yesterday morning, forcing BEC to load shed for the majority of the day. According to Mr Miller, the load shedding was expected to continue last night.

Click here to read more at The Tribune